Massachusetts budget approval allows utilities to recoup added cost of hydropower corridor
View
Date:2025-04-17 20:23:02
PORTLAND, Maine (AP) — A budget signed by Massachusetts Gov. Maura Healey this week will allow utilities to raise rates to make up for hundreds of millions of dollars in additional costs to complete a transmission line to bring Canadian hydropower to the New England electricity grid.
The head of Central Maine Power Co.'s corporate parent Avangrid has said the cost of the $1 billion project grew to $1.5 billion as litigation delayed construction and inflation caused prices to creep upward.
Legislation included the supplemental budget adopted Monday allows transmission service agreements to be renegotiated and additional costs to be passed along to Massachusetts ratepayers to cover the added costs.
Avangrid provided the increased costs to Massachusetts’ electricity distribution companies to adjust the rate in the parties’ transmission services agreements, which would be subject to Department of Public Utilities review and approval, Avangrid spokesperson Leo Rosales said in a statement Tuesday.
He praised Healey and lawmakers for taking action to “deliver this critical project and needed clean power to benefit the entire New England region.”
Avangrid partnered with Hydro-Quebec on the New England Clean Energy Connect to supply 1,200 megawatts of hydropower to meet green energy goals in Massachusetts. That would be enough electricity to power about a million homes.
The 145-mile (233-kilometer) transmission line will stretch from Lewiston, Maine, to the Canadian border.
It received all regulatory approvals but was plagued by delays, litigation and a referendum in which https://apnews.com/article/election-2021-maine-hydropower-line-54dea1a948e9fc57a667280707cddeb7
It was allowed to move forward after a Maine jury concluded that the developers had a constitutional right to proceed despite the referendum.
Construction resumed in August on a transmission hub that’s critical to the project in Lewiston. But it’s unclear when other work will restart.
Workers had already begun removing trees and setting utility poles on a disputed portion of the project, a new 53-mile (85-kilometer) section cut through the woods in western Maine, before the project was put on hold.
The project was envisioned to meet Massachusetts’ clean energy goals, and the cost is fully borne by ratepayers in that state.
However, supporters say electricity would lower energy costs across New England as well as reduce carbon pollution.
veryGood! (87639)
Related
- Most popular books of the week: See what topped USA TODAY's bestselling books list
- Convicted killer attacked by victim's stepdad during sentencing in California courtroom
- Marlena Shaw, 'California Soul' singer, dead at 81: 'Beloved icon and artist'
- Across Germany, anti-far right protests draw hundreds of thousands - in Munich, too many for safety
- 2 killed, 3 injured in shooting at makeshift club in Houston
- That 'True Detective: Night Country' frozen 'corpsicle' is unforgettable, horrifying art
- Russia oil depot hit by Ukrainian drone in flames as Ukraine steps up attacks ahead of war's 2-year mark
- Jamaica cracks down on domestic violence with new laws aimed at better protecting victims
- Residents worried after ceiling cracks appear following reroofing works at Jalan Tenaga HDB blocks
- Gaza doctor describes conditions inside his overwhelmed hospital as Israeli forces advance
Ranking
- Appeals court scraps Nasdaq boardroom diversity rules in latest DEI setback
- Taylor Swift cheers on Travis Kelce as the Kansas City Chiefs again take on Buffalo Bills
- Djokovic reaches the Australian Open quarterfinals, matching Federer's Grand Slam record
- Latest EPA assessment shows almost no improvement in river and stream nitrogen pollution
- Friday the 13th luck? 13 past Mega Millions jackpot wins in December. See top 10 lottery prizes
- Jared Goff throws 2 TD passes, Lions advance to NFC title game with 31-23 win over Buccaneers
- When does 'The Bachelor' start? Season 28 premiere date, how to watch and stream
- David Gail, soap star known for 'Beverly Hills, 90210' and 'Port Charles,' dies at 58
Recommendation
Angelina Jolie nearly fainted making Maria Callas movie: 'My body wasn’t strong enough'
Oscar nomination predictions: Who's in for sure (what's up, RDJ!) and who may get snubbed
Nick Dunlap becomes first amateur to win a PGA Tour event in 33 years at American Express
Houthi rebels launch missile attack on yet another U.S.-owned commercial ship, Pentagon says
Macy's says employee who allegedly hid $150 million in expenses had no major 'impact'
Proposed federal law would put limits on use of $50 billion in opioid settlements
Latest EPA assessment shows almost no improvement in river and stream nitrogen pollution
No charges for 4 Baltimore officers who fatally shot an armed man after he fired at them